Project Management training in Lausanne · canton of Vaud"It will be ready by Friday": why do we underestimate the duration of our own projects?

A team announces a deadline that seems reasonable. Three weeks later, it must be postponed, without any major incident explaining it. People then speak of bad luck or lack of rigour. Research suggests a more precise reading: the very way in which a forecast is constructed can favour optimism. The managerial question is therefore not only "who got it wrong?", but "on what information was the estimate based?".
1. What the literature establishes
Roger Buehler, Dale Griffin and Michael Ross (1994, Journal of Personality and Social Psychology) study what they call the "planning fallacy". In several studies, participants, often students, forecast the completion date of their own tasks; the majority finish later than expected, even though they acknowledge having missed their deadlines in the past. The authors show that people focus on future scenarios rather than on their past experiences. Buehler, Griffin & Ross, 1994 — Exploring the planning fallacy
2. The neglected distinction: inside view and outside view
Daniel Kahneman and Dan Lovallo (1993, Management Science) propose a useful distinction. The "inside view" constructs the forecast from the steps of the project in question; the "outside view" starts from the distribution of outcomes obtained by comparable projects. The first seems more informed because it is detailed, but it tends to ignore obstacles that are not yet visible. The article is a conceptual analysis supported by the literature, not an experimental demonstration of the effectiveness of the outside view in business. Kahneman & Lovallo, 1993 — Timid choices and bold forecasts

3. Why detail does not protect
Breaking down a project into tasks seems to make the estimate more reliable. This is only true if the breakdown also integrates rework, validations, absences and dependencies. A detailed plan can instead reinforce confidence in a scenario without uncertainty. Research does not say that planning is useless; it indicates that the apparent precision of a plan does not guarantee the accuracy of its total duration.
4. The limitations of the data
Studies by Buehler and colleagues focus mainly on individual tasks and university samples; a collective project involves negotiations, trade-offs and contractual constraints that they do not reproduce. The article by Kahneman and Lovallo does not provide a measure of the magnitude of the bias in organizations. Moreover, a delay may result from a legitimate change in scope rather than from an estimation error. Transposing these works to a team remains a cautious inference. (our executive and employee training programmes)
5. Defensible conditions for practice
A defensible approach consists of comparing the detailed estimate against an external reference: how long did the team's last three or four comparable projects actually take? The gap between the two figures becomes a matter for discussion, not a mistake. It is also useful to distinguish delays due to scope from those due to estimation. These conditions reflect the distinctions in the research; their effect on project timeliness has not been demonstrated by the cited articles.
6. A modest test in Lausanne
Before validating a deadline, a team could note two figures on the same page: the duration from its planning and the actual duration of its last similar projects. At closure, it compares the two forecasts to the result and notes the main cause of the gap. This record proves no causal effect; it makes visible the forgotten reference. The question can be explored in SHR project management training To go further: explore the Project Management training in Lausanne in the canton of Vaud, or browse our executive and employee training programmes in Switzerland.
In pictures: Project Management in Lausanne



- project management
- Lausanne
- research
- training lausanne
Our training by canton
- VaudProject Management
- GenevaProject Management
- ZurichProject Management
- BernProject Management
- Basel-CityProject Management
- TicinoProject Management
- FribourgProject Management
- NeuchâtelProject Management
- LucerneProject Management
- St. GallenProject Management
- ValaisProject Management
- JuraProject Management
- ZugProject Management